PMP proper noun in English explanation
 瀏覽922|回應0推薦0

愛玩的孩子
等級:8
留言加入好友
Work breakdown structure-
A deliverable-oriented grouping of the work involved in a project that defines the total scope of the project

WBS dictionary-
A document that describes detailed information about each WBS item
Work package-
a task at the lowest level of the WBS

Activity attributes-
Information about each activity﹑such as predecessors﹑successors﹑logical relationships﹑leads and lags﹑resource requirements﹑constraints﹑imposed dates﹑and assumptions related to the activity

Buffer-
Additional time to complete a task﹑added to an estimate to account for various factors

Activity sequencing-
Identifying and documenting the relationships between project activities

Crashing-
A technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost

Burst-
When a single node is followed by two or more activities on a net-work diagram

Fast tracking-
A schedule compression technique in which you do activities in parallel that you would normally do in sequence

Free slack-
The amount of time an activity can be delayed without delaying the early start of any immediately following activities

Milestone-
A significant event that normally has no duration on a project; serves as a marker to help in identifying necessary activities,setting schedule goals,and monitoring progress

Multitasking-
When a resource works on more than one task at a time